Alley No. 42 Reconstruction

Alley 42 is bounded by Grand Ave, Frame Ave, Garfield Ave. and Wabash Ave.

Project Update April 30, 2021

As part of the City’s Alley Reconstruction program, Alley #42 (Bordered by:  Grand, Frame, Garfield, Wabash) will be reconstructed in 2021. 

 

Work Completed This week (4/26 – 4/30)

  • East/west leg of the new alley pavement poured
  • Some concrete driveway aprons replaced on the north/south leg
  • Alley driveway entrance apron and sidewalk along Wabash Ave. poured

 

Planned Work Next Week (5/3 – 5/7)

  • Complete grading and preparation work for the driveway aprons to the alley
  • Concrete drive approach replacements along both legs
  • HMA driveway replacements along both legs (tentative)
  • Alley driveway entrance and sidewalk pouring on Frame Ave., and Garfield Ave.

 

Traffic Control/Access

  • Alley 42 is closed to all vehicle access.

 

All the dates and times above are subject to change and are weather dependent.  I will update the group if anything changes from the above information.  If you have any questions or concerns regarding the project, please feel free to contact me. 

 

Project Contact

Brandon Schweenn, P.E.
Project Engineer
262-524-3585
Email: bschwenn@waukesha-wi.gov


IMG_1626