Project Update: April 9, 2021
The reconstruction project will consist of the following work:
- Sanitary sewer and lateral replacements/rehabilitations
- New watermain and services
- Storm sewer replacements and additions
- New concrete roadway and curb and gutter
- Upgraded ADA pedestrian crossings
- Sod restoration
Past Activities (Week of April 5th)
- Sanitary sewer mainline work was completed. The mainline work took place between National Ave and E Main St.
- Contractor started working on the sanitary sewer laterals.
Future Work (Week of April 12th ):
- Contractor will continue working on the sanitary sewer laterals between E Main St & Arcadian Ave.
- At completion of sanitary sewer laterals, construction activities will shift from sanitary sewer to watermain.
Traffic Restrictions:
- Perkins Avenue – Closed to through traffic (open to local traffic only). Resident & business driveway access will be maintained.
Please feel free to call or email with any questions or concerns.