Woodfield Dam Stream Restoration

Project Update: September 18, 2020


The Contractor, RLP Diversified, started rock and debris removal, hydroseeding, and fertilizing in the turf areas of Woodfield Park. Areas of weeds along the creek are also being cut down today. Remaining work scheduled for the next week or so includes planting of wetland plugs, and installing the fence over the pedestrian bridge. Some photos of work from today are shown below.

 