Artificial Turf Install Frame and Mindiola Parks

Project Update: Jan 4, 2021 (Final Update) 

Frame Park:

 

Frame Park is substantially Complete

 

Mindiola Park:

 

Mindiola Park is substantially Complete.  The Contractor will return in the spring to finish the landscaping.


The project consists of the following:

Frame Park Baseball:

  • Installation of Synthetic Turf for infield and outfield of Ball Diamond
  • Reconstruction of Dugouts and Fencing

Mindiola Park Soccer Field

  • Approximately 95,000 Sq. Ft Synthetic Turf Installation
  • Back Up Net System and Fencing
  • Field Lightening

If you have any concerns or questions please contact the Project Manager Below:


Katie Jelacic, P.E.
Project Engineer
262-524-3587 (o)
262-349-6511 (c)

Mindiola Soccer Field

Jan 4 Update Mindiola

Frame Park Ball Diamond

Nov 12 Frame 2