2020 Resurfacing of Rolling Ridge Drive

Project Update: October 9, 2020 (Final Update)

This week the contractor was able to finish all of the pavement markings on the project, and started to prep the remaining areas for sod.

 

The contractor should be finishing all of the restoration by the end of next week. Over the up and coming weeks, the City will be doing its final walkthrough on the project noting any deficiencies for the contractor to fix.

 

This will be my final update for this project.

 

If you have any questions, please contact me.

 

Final Draft Area 1 and 2 Alternative Storm Water Report

This year the resurfacing program is in the Rolling Ridge area of the City.  The project will consist of sewer manhole and storm inlet repairs, curb and gutter repairs, upgrading handicap ramps to meet current ADA standards, milling and overlaying/paving with asphalt pavement.

Public Notification Letter

Also included in this project is phase I of the flood mitigation improvements in this areas.  this will include up-sizing the existing culvert crossings along Rolling Ridge Drive from Devonshire Ct. to University Drive.

Craig Ausen, P.E.

Project Engineer

City of Waukesha – Engineering Division

130 Delafield St. Waukesha, WI 53188

O: (262) 524-3589

C: (262) 349-6516

2020-Rolling Ridge
2020 Rolling Ridge DPW