Sanitary Sewer Lining & Manhole Rehabilitation

Project Update: August 28, 2020

This project involves rehabilitating concrete sanitary sewers using a trenchless lining process along Sunset Dr from S Grand Ave to Tenny Ave and in Heyer Park from the intersection of Larchmont Dr & Heyer Dr to Les Paul Parkway.   Sanitary manholes will also be repaired as needed.

 

This week’s work:

  • None

 

Next week’s work:

  • Line last sanitary manhole in intersection of S East Ave & Sunset Dr.  This work will occur at night (after 7pm) to minimize impact on traffic.
  • Repair to asphalt patches in intersection of Sunset Dr & Tenny Ave and in intersection of Heyer Dr & Larchmont Dr

 

Streets with restricted access for the next week:

  • Some short-term traffic movements will be restricted in the S East Ave & Sunset Dr intersection when work is completed on the sanitary manhole in the center of the intersection.  This would occur at night (after 7pm).
  • Some short-term traffic movements will be restricted in the Sunset Dr & Tenny Ave intersection when repair to the asphalt patch is completed in the center of the intersection.

 

Streets that will have No Access for the next week:

  • None

Please contact the Project Engineer with any questions.


Jonathan Schapekahm, P.E.
Project Engineer / CMOM Coordinator
City of Waukesha
P:262-524-3584