Eastside Beltline Sanitary Sewer Relay & Lining

Project Update: August 30, 2019

This project includes the installation of a replacement sanitary sewer within the footprint of the former railroad ROW located between Arcadian Ave and National Ave.

This week’s work:

  • Sanitary manhole liners were installed.

Next week’s work:

  • Sewer televising is expected this coming week.

Streets with restricted access for the next week:

  • None

Streets that will have No Access:

  • None

The City of Waukesha will be relaying sanitary sewer from Arcadian Ave to National Ave. Existing sanitary sewer will also be lined from National Ave to E Main St. The project lies within the footprint of the former railroad ROW. Therefore, traffic restrictions are not foreseen throughout this project duration.

The project was awarded at the March 7th Common Council meeting to Super Excavators. The contractor is planning to being utility construction as early as May 6th (weather dependent) and the completion date is September 14, 2019.

To receive project updates please send your e-mail address to tmiles@waukesha-wi.gov. Updates will be sent weekly or if conditions change.


Tom Miles
City of Waukesha Department of Public Works – Engineering Division
130 Delafield Street | Waukesha, WI 53188
O:262-524-3600
D: 262-524-3578

tmiles@waukesha-wi.gov | www.waukesha-wi.gov