Water Utility's E. Main St. Utility and Street Reconstruction Project

Project Update: Nov 8 , 2019

This week, the final section of curb and gutter, east of Perkins, was installed on both sides of the new road. Driveways, sidewalks, handicap ramps, and other miscellaneous concrete items are also being finished up. The contractor will be on site tomorrow pouring concrete and plans to install pavement marking on Sunday. Weather permitting, we anticipate opening the road, including the intersection at Perkins, by mid to late next week. The intersection at Perkins and Main will be controlled by temporary stop signs for a few more weeks until the signal is up and operational.

Please contact me with any questions.

Chris J. Walter, P.E.
Technical Services Manager
Waukesha Water Utility | P. O. Box 1648 | Waukesha, Wisconsin 53187-1648 | (262) 521-5272
(262) 409-4460 | (262) 901-5886 | * cwalter@waukesha-water.com | www.waukesha-water.com

IMG_6690