Concrete Sewer Lining Projects

During the 2017 Construction Season there will be 2 separate Concrete Sewer Lining Projects. They will be depicted as the West Project and the East Project:

These projects will involve reconstructing or repairing manholes as needed, cleaning the sewers, installing a structural liner in the sewer, sealing the joint between private service laterals and the public sewer, and any restorations that may be necessary as a result of the work.  

The actual installation of the structural liner normally requires less than 24 hours to complete for each pipe section.  During this time, service lateral connections will be sealed off at the sewer main in the street. Once the liner is installed, the service lateral will be reopened and sewer use can return to normal. If a resident’s lateral connection will be impacted by the work, they will be asked to make limited use of their toilet facilities and refrain from doing laundry during the time period that the service lateral is sealed off. A few days prior to installing the liner, the contractor will place a notice on the resident’s door as to the actual date and time of the limited water use period.

Concrete Sanitary Sewer Lining – West Project

Project Update April 21, 2017     

This week the contractor finalized the two spot repairs that were made to the sewer on MacArthur Rd between Burrie Ln and S. Grandview Blvd. 

Next week, the contractor will line the 24” sewer on MacArthur Rd between Burrie Ln and S. Grandview Blvd.

 

As part of the City’s sanitary sewer maintenance program, the sanitary sewer from the intersection of S. Comanche Ln & Crestwood Dr to the Clean Water Plant will be rehabilitated using a trenchless lining process.   The sewers to be lined range in size from 15 inches to 30 inches in diameter with a total length of approximately 9700 feet.
 
As part of the City of Waukesha’s sanitary sewer maintenance program, the sewer from the intersection of S. Comanche Ln & Crestwood Dr to the Clean Water Plant will be rehabilitated using a trenchless lining process.  The lining process does not involve the time consuming, disruptive, and expensive excavation that digging up and replacing the sewer would require.  The project has been contracted to Visu-Sewer, W230 N4855 Betker Drive, Pewaukee, WI.  Work is to begin on February 6 with the project complete by May 26.

Concrete sewer lining location map WEST

Concrete Sanitary Sewer Lining – East Project



As part of the City of Waukesha’s sanitary sewer maintenance program, several the sewers will be rehabilitated using a trenchless lining process.  They are:

•    Sewer along a section of Jefferson Ave
•    Sewer along Gail St
•    Sewer along sections of White Rock Ave
•    Sewer along a section of Perkins St

The project has been contracted to Visu-Sewer, W230 N4855 Betker Drive, Pewaukee, WI.  Work is to begin in the spring with the project complete by October 6.

Contact Information:
Jonathan Schapekahm, P.E.
Project Engineer/CMOM Coordinator
City of Waukesha
262-524-3584
jschapekahm@waukesha-wi.gov


Concrete sewer lining location map EAST